Somers finishes $162,000 flood study ranking projects and estimating costs
Wisconsin Digest
Last updated: November 25, 2026

Somers has finished a flood study that ranks projects to ease flooding across several flood-prone watersheds in the Kenosha County village, with a $121,500 state grant covering most of the bill.
That state share came to 75 percent of the grant's $162,000 total.
Work wrapped up Sept. 15, leaving the village with planning-level cost estimates for future projects and a list of possible funding sources to pay for them.
In a project summary, Wisconsin Emergency Management said the project "successfully met its objectives by identifying, evaluating, and prioritizing flood mitigation opportunities across the study watersheds."
Using topographic surveys of the watersheds along with hydrologic and hydraulic modeling, the study weighed regrading waterways, improving culverts and storm sewers, and adding green infrastructure practices.
Along part of the Pike River, a field assessment checked on upkeep such as clearing debris, shoring up streambanks and managing sediment.
Village Board members and residents heard the findings at two presentations, where they were asked for feedback.
Everything went into a final report. It "will assist the Village with future flood mitigation planning," the agency said.
Copies of the report, its appendices and the study's data are available by emailing the agency's hazard mitigation address.